Lead paint stripped from the siding, fascia and window frames of a 1950s ranch house
Example project

- Home
- 1950s single-story ranch house in Livermore with horizontal wood siding, under oak trees
- Original request
- Take the lead paint off the siding, fascia and window frames before the house is repainted
- Testing
- Lead paint on the siding, the fascia and the window frames
- Surfaces
- The siding on the two long sides, the fascia and the window frames, about 950 sq ft
- Notice
- CDPH Form 8551 posted and sent at least five days ahead; neighbors told in writing
- Estimated cost
- $10,000
Scope of work
Leaves and acorns swept up, plastic laid along the full base of each long wall and out past the drip line, the siding, fascia and window frames stripped with paste stripper and wet scraping, waste bagged each day, primer and two coats of lead-free paint, and a clearance check of the ground and the sills. The roof and any rotten boards are not part of this price.
Project overview
In this example, the owners of a 1950s ranch house in Livermore plan to repaint the whole outside and ask a painter what to do about the old coats. A test shows lead paint on the siding, the fascia and the window frames.
They want it gone before the new paint goes on, so the job is abatement. Form 8551 is posted at the house and sent to CDPH at least five days ahead, and the neighbors are told in writing. The oaks drop leaves and acorns onto the work area, so the ground is swept and the plastic is laid out past the drip line each time.
The goal
The goal is siding and trim with no lead paint left on them and soil free of chips under the oaks.
Process
- Notice Form 8551 posted and sent; letters to the neighbors.
- Setup Ground swept, plastic laid along each long wall and out past the drip line.
- Stripping Siding, fascia and window frames stripped wet, waste bagged daily.
- Paint Bare wood primed and given two coats.
- Clearance Ground and sills checked for chips and dust before the plastic comes down.
Planning right
- Never dry-scrape or pressure-wash old siding. Chips and wash water carry the lead into the soil.
- Boards that are soft or split behind the paint are replaced at extra cost.
- Plastic is weighed down and checked each morning, since wind and falling leaves move it.
- Keep the clearance report where the next painter can find it.